You do not expect the types of variances that have occurred on the project to date to
Question:
You do not expect the types of variances that have occurred on the project to date to continue.
If BAC = 800, ETC = 275, PV = 300, ACC = 200, EV = 250, and CPIC = 1.25, what is the EAC?
A. 640 B. 750 C. 600 D. 550