Your project is nearing completion of the first phase. Your key stakeholder for this phase reminds you

Question:

Your project is nearing completion of the first phase. Your key stakeholder for this phase reminds you that she will not accept the deliverable unless it measures 3 centimeters exactly. If the measurements are off, phase 2 will be delayed, and the entire project will be at risk. This is an example of which of the following?

A. Delivery acceptance criteria B. Success criteria C. Critical success factor D. KPI

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: