Your project is nearing completion of the first phase. Your key stakeholder for this phase reminds you
Question:
Your project is nearing completion of the first phase. Your key stakeholder for this phase reminds you that she will not accept the deliverable unless it measures 3 centimeters exactly. If the measurements are off, phase 2 will be delayed, and the entire project will be at risk. This is an example of which of the following?
A. Delivery acceptance criteria B. Success criteria C. Critical success factor D. KPI