Your project is to be performed outdoors. You are only four days from the big event, and
Question:
Your project is to be performed outdoors. You are only four days from the big event, and there is a hurricane headed for shore. This is an example of which of the following?
A. Risk B. Assumption C. Deliverable D. Constraint