Here is a network with the activity times shown in days: G(5) F(4) E(2) D(5) C(4) B(3)
Question:
Here is a network with the activity times shown in days:
G(5)
F(4)
E(2)
D(5)
C(4)
B(3)
A(7)
a. Find the critical path.
b. The following table shows the normal times and the crash times, along with the associated costs for each activity If the project is to be shortened by four days, show which activities, in order of reduction, would be shortened and the resulting cost.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations And Supply Management: The Core
ISBN: 9780073403335
2nd Edition
Authors: F. Robert Jacobs, Richard Chase
Question Posted: