The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME
Question:
The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
a. Draw the network.
b. What is the critical path?
c. How many weeks will it take to complete the project?
d. How much slack does activity B have?
Step by Step Answer: