A construction project is broken down into the following 10 activities: Activity Immediate Predecessor Time (weeks) 1
Question:
A construction project is broken down into the following 10 activities:
Activity Immediate Predecessor Time (weeks)
1 2
3 4
5 6
7 8
9 10
—
1 1
1 2, 3 3
4 5
6, 7 8, 9 4
2 4
3 5
6 2
3 5
7
a. Draw the network diagram.
b. Find the critical path.
c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks?