Assume that Product Z is made of two units of A and four units of B. A

Question:

Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four D. D is made of two units of E.

Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.

Fifty units are required in Period