Chapman Pharmaceuticals, a large manufacturer of drugs, has this aggregate demand forecast (in thousands of liters) for

Question:

Chapman Pharmaceuticals, a large manufacturer of drugs, has this aggregate demand forecast (in thousands of liters) for a liquid cold medicine.

The firm has a normal production rate of 90 thousand liters per month, and the initial inventory is 100 thousand liters. Inventory-holding costs are $30 per 1,000 liters per month, regular-time production costs are $400 per 1,000 liters. Overtime costs an additional 20 percent, and undertime costs an additional 12 percent. Assume that there are no lost sales or rate change costs. Use the Agg Plan – Level and Agg Plan – Chase Excel templates to compute the costs of a level production rate of 90 thousand liters per month and a chase demand production plan.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations And Supply Chain Management

ISBN: 9780357131695

2nd Edition

Authors: David A. Collier, James R. Evans

Question Posted: