For the network shown: G(4) D(6) C(8) B(10) A(5) E(7) F(4) a. Determine the critical path and

Question:

For the network shown:

G(4)

D(6)

C(8)

B(10)

A(5) E(7)

F(4)

a. Determine the critical path and the early completion time in weeks for the project.

b. For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at your schedule.

Activity Normal Time Normal Cost Crash Time Crash Cost A

B C

D E

F G

5 10 8

6 7

4 4

$ 7,000 12,000 5,000 4,000 3,000 6,000 7,000 3

7 7

5 6

3 3

$13,000 18,000 7,000 5,000 6,000 7,000 9,000

 LO.1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations And Supply Chain Management

ISBN: 9780077151638

14th Edition

Authors: F. Robert Jacobs , Richard Chase

Question Posted: