For the network shown: G(4) D(6) C(8) B(10) A(5) E(7) F(4) a. Determine the critical path and
Question:
For the network shown:
G(4)
D(6)
C(8)
B(10)
A(5) E(7)
F(4)
a. Determine the critical path and the early completion time in weeks for the project.
b. For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at your schedule.
Activity Normal Time Normal Cost Crash Time Crash Cost A
B C
D E
F G
5 10 8
6 7
4 4
$ 7,000 12,000 5,000 4,000 3,000 6,000 7,000 3
7 7
5 6
3 3
$13,000 18,000 7,000 5,000 6,000 7,000 9,000
LO.1
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations And Supply Chain Management
ISBN: 9780077151638
14th Edition
Authors: F. Robert Jacobs , Richard Chase
Question Posted: