In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts,
Question:
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week.
WEEK NUMBER ITEM J 0 1 2345 Gross requirements 75 50 70 On-hand 40 Net requirements Planned order receipt Planned order release