In the project network shown in the following figure, the number alongside each activity designates its known
Question:
In the project network shown in the following figure, the number alongside each activity designates its known duration in weeks. Determine the following:
(a) Earliest and latest start and finish times for each activity
(b) Earliest time that the project can be completed
(c) Slack for activities
(d) Critical activities
(e) Critical path