The following activities are part of a project to be scheduled using CPM: Activity Immediate Predecessor Time
Question:
The following activities are part of a project to be scheduled using CPM:
Activity Immediate Predecessor Time (weeks)
A B
C D
E F
G
—
A A
C B, D D
E, F 6
3 7
2 4
3 7
a. Draw the network.
b. What is the critical path?
c. How many weeks will it take to complete the project?
d. How much slack does activity B have?
LO.1