There is an 82 percent chance the project below can be completed in X weeks or less.

Question:

There is an 82 percent chance the project below can be completed in X weeks or less.

What is X?

C B D E

A Activity Most Optimistic Most Likely Most Pessimistic A

B C

D E

2 3

1 6

4 5

3 3

8 7

11 3

5 10 10

 LO.1