There is an 82 percent chance the project below can be completed in X weeks or less.
Question:
There is an 82 percent chance the project below can be completed in X weeks or less.
What is X?
C B D E
A Activity Most Optimistic Most Likely Most Pessimistic A
B C
D E
2 3
1 6
4 5
3 3
8 7
11 3
5 10 10