You are responsible for wiring a smart 12-story building in downtown Chicago. The project network and basic

Question:

You are responsible for wiring a smart 12-story building in downtown Chicago. The project network and basic information is shown in the following table. The time is in weeks. Your promotion depends on the successful completion of this project in 20 weeks.


a.  Draw the project network and compute expected times and variances for each activity.

b. What is the critical path and expected time of completion?

c. What activity has the largest slack time and how much is it?

d. What is the probability of completing the project in 20 weeks using PERT?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations And Supply Chain Management

ISBN: 9780357131695

2nd Edition

Authors: David A. Collier, James R. Evans

Question Posted: