11. The product structure tree for a drafting table (part A) is shown below. The number of...
Question:
11. The product structure tree for a drafting table (part A) is shown below. The number of an item required to make one unit of the item above it is indicated in front of the item. The lead time required to purchase an item or to produce it from the component(
s) at the next lower level is indicated in parentheses following each item. The company uses lot-forlot ordering and plans to complete 175 tables in week 7 and 250 in week 8. No other requirements for the table or its components are planned within this lead time. The on-hand balance and scheduled receipts values for the sides and legs are given in the table beside the product structure tree. Construct time-phased inventory records for the side and the legs.
Step by Step Answer:
Operations Management Providing Value In Goods And Services
ISBN: 9780030262074
3rd Edition
Authors: Dilworth, James B