9. Shown at the top of page 661 is an AON network for a PERT schedule on

Question:

9. Shown at the top of page 661 is an AON network for a PERT schedule on a project.

The three time estimates, in weeks, for each activity are given in the table below.

a. Compute 1, for each activity.

b. Determine the expected completion time for the project.

c. What is the critical path?

d. Give the expected slack for each activity that is not on the critical path.