A process at Amit Eynan Bottling Company that is considered in control measures liquid in ounces. Below

Question:

A process at Amit Eynan Bottling Company that is considered in control measures liquid in ounces. Below are the last 12 samples taken. The sample size = 4.

SAMPLES 1 2 3 4 5 6 7 8 9 10 11 12 20.2 19.9 19.8 20.1 19.8 19.7 20.2 20.1 20.0 19.9 20.1 19.9 20.1 19.9 19.9 19.9 20.1 19.6 20.1 20.1 19.9 19.8 20.1 19.4 19.8 19.7 20.0 19.9 20.1 19.7 19.9 19.8 20.1 20.1 19.8 19.7 19.9 20.1 20.1 19.8 19.9 19.4 19.9 19.7 19.8 19.9 19.9 19.8

a) What are the control limits for the mean chart?

b) What are the control limits for the range chart?

c) Graph the data. Is the process in control?

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Sustainability And Supply Chain Management

ISBN: 9781292295039

13th Global Edition

Authors: Jay Heizer, Barry Render, Chuck Munson

Question Posted: