An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day
Question:
An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard’s schedule.
JOB DUE DATE REMAINING TIME (DAYS)
A 212 6 B 209 3 C 208 3 D 210 8 In what sequence would the jobs be ranked according to the following decision rules:
a) FCFS
b) SPT
c) LPT
d) EDD
e) Critical ratio Which is best and why? Which has the minimum lateness? L 0 1