An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard’s schedule.

JOB DUE DATE REMAINING TIME (DAYS)

A 212 6 B 209 3 C 208 3 D 210 8 In what sequence would the jobs be ranked according to the following decision rules:

a) FCFS

b) SPT

c) LPT

d) EDD

e) Critical ratio Which is best and why? Which has the minimum lateness? L 0 1 