Consider a process consisting of three resources. Assume there exists unlimited demand for the product. Resource
Question:
Consider a process consisting of three resources. Assume there exists unlimited demand for the product.
• Resource 1 has a processing time of 6 minutes per unit.
• Resource 2 has a processing time of 3 minutes per unit.
• Resource 3 has a processing time of 5 minutes per unit.