Drew Rosen Automation Company estimates the data entry and verifying times for four jobs as follows: L
Question:
Drew Rosen Automation Company estimates the data entry and verifying times for four jobs as follows: L 0 1
JOB DATA ENTRY (HOURS) VERIFY (HOURS)
A 2.5 1.7 B 3.8 2.6 C 1.9 1.0 D 1.8 3.0 In what order should the jobs be done if the company has one operator for each job? Illustrate the time-phased flow of this job sequence graphically.