Flores Manufacturing, Inc., is moving to kanbans to support its electronic-board assembly lines. Determine the size of
Question:
Flores Manufacturing, Inc., is moving to kanbans to support its electronic-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed.
Setup cost = +25 Annual holding cost = +200 per subassembly Daily production = 400 subassemblies Annual usage = 50,000 1= 50 weeks * 5 days each
* daily usage of 200 subassemblies2 Lead time = 6 days Safety stock = 1 day>s production of subassemblies L01