Four employees are to be assigned to four different jobs. The time per job per employee in

Question:

Four employees are to be assigned to four different jobs. The time per job per employee in minutes is given in the table below. L 0 1 

JOB EMPLOYEE 1 2 3 4 A 8 10 17 9 B 3 8 5 6 C 10 12 11 9 D 6 13 9 7 Find the optimal assignment of employees to jobs to minimize the total completion time.