Question: Henri recently learned about global priority rules. He is interested in the slack over remaining operations (S/RO) rule. (a) Using the data in Problem 5,
Henri recently learned about global priority rules. He is interested in the slack over remaining operations (S/RO) rule.
(a) Using the data in Problem 5, determine the sequence Henri should follow if he uses the S/RO (slack over re- maining operations) priority rule.
(b) Based on the sequence developed in Part
a, calculate the following performance measures: makespan, mean job flow time, average number of jobs in the system, mean job lateness, mean job tardiness, and maximum tardiness.