Shown below is an AOA network for a small project. The three time estimates, in weeks, for
Question:
Shown below is an AOA network for a small project. The three time estimates, in weeks, for each activity are shown on each arrow.
(a) Compute the expected time for each activity.
(b) Find the expected duration of the project.
(c) Find the slack at the nodes that are not on the critical path.
(d) Compute the standard deviation of the critical path.
(e) Using the standard deviation of the critical path as the standard deviation of the project’s duration, compute the probability of completing the project in 35 weeks or less.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management Providing Value In Goods And Services
ISBN: 9780030262074
3rd Edition
Authors: Dilworth, James B
Question Posted: