The crash cost per period: a) Is the difference in costs divided by the difference in times
Question:
The crash cost per period:
a) Is the difference in costs divided by the difference in times (crash and normal).
b) Is considered to be linear in the range between normal and crash.
c) needs to be determined so that the smallest cost values on the critical path can be considered for time reduction first.
d) all of the above.