The difference between a gross material requirements plan (gross MRP) and a net material requirements plan (net MRP) is:

a) The gross MRP may not be computerized, but the net MRP must be computerized.

b) The gross MRP includes consideration of the inventory on hand, whereas the net MRP doesn’t include the inventory consideration.

c) The net MRP includes consideration of the inventory on hand, whereas the gross MRP doesn’t include the inventory consideration.

d) The gross MRP doesn’t take taxes into account, whereas the net MRP includes the tax considerations.

e) The net MRP is only an estimate, whereas the gross MRP is used for actual production scheduling.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Sustainability And Supply Chain Management

ISBN: 234357

12th Edition

Authors: CHUCK MUNSON & AMIT SACHAN AND . JAY HEIZER , BARRY RENDER

Question Posted: