Question: WAT uses two resources for each product that it builds: direct labor and machine time. From historical records, WAI calculates the following planning factors: Direct
WAT uses two resources for each product that it builds: direct labor and machine time. From historical records, WAI calculates the following planning factors: Direct labor for standard corkscrew is 0.20 hours. Direct labor for deluxe corkscrew is 0.50 hours. Machine time for standard corkscrew is 0.10 hours. Machine time for deluxe corkscrew is 0.30 hours Calculate the capacity needed for the MPS developed in Problem 18