Anju Chaudhary is developing a program in leadership training for middle-level managers. She has listed a number

Question:

Anju Chaudhary is developing a program in leadership training for middle-level managers. She has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Time (days) Immediate Predecessor(s) Activity A 2 B 5 D 10 A, D 3 E, F G


a) Develop an AON network for this problem.
b) What is the critical path?