Given the projects displayed in Table 18.21, if SPT is used to sequence the jobs, what is

Question:

Given the projects displayed in Table 18.21, if SPT is used to sequence the jobs, what is the average flow time of the projects (in hours)?

Project P1 P2 P3 P4 P5 P6 P7 P8 Processing time (hours) 4 1 2 36 5 1 0.5