19 Hallco runs a day shift and a night shift. No matter how many units are produced,...
Question:
19 Hallco runs a day shift and a night shift. No matter how many units are produced, the only production cost during a shift is a setup cost. It costs $8,000 to run the day shift and $4,500 to run the night shift. Demand for the next two days is as follows: day 1, 2,000; night 1, 3,000; day 2, 2,000; night 2, 3,000. It costs $1 per unit to hold a unit in inventory for a shift. Determine a production schedule that minimizes the sum of setup and inventory costs. All demand must be met on time.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Research Applications And Algorithms
ISBN: 9780534380588
4th Edition
Authors: Wayne L. Winston
Question Posted: