19 Hallco runs a day shift and a night shift. No matter how many units are produced,...

Question:

19 Hallco runs a day shift and a night shift. No matter how many units are produced, the only production cost during a shift is a setup cost. It costs $8,000 to run the day shift and $4,500 to run the night shift. Demand for the next two days is as follows: day 1, 2,000; night 1, 3,000; day 2, 2,000; night 2, 3,000. It costs $1 per unit to hold a unit in inventory for a shift. Determine a production schedule that minimizes the sum of setup and inventory costs. All demand must be met on time.