2. Construct the project network comprised of activities A to P that satisfies the following precedence relationships:
Question:
2. Construct the project network comprised of activities A to P that satisfies the following precedence relationships:
(a) A, B, and C, the first activities of the project, can be executed concurrently.
(b) D, E, and F follow A.
(c) I and G follow both Band D.
(d) H follows both C and G.
(e) K and L follow 1.
(f) J succeeds both E and H.
(g) M and N succeed F, but cannot start until both E and H are completed.
(h) 0 succeeds M and I.
(i) P succeeds 1, L, and o.
(j) K, N, and P are the terminal activities of the project.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: