3 Consider the project network in Figure 40. For each activity, you are given the estimates of...

Question:

3 Consider the project network in Figure 40. For each activity, you are given the estimates of

a, b, and m in Table 18. Determine the critical path for this network, the total float for each activity, the free float for each activity, and the probability that the project is completed within 40 days.

Also set up the LP that could be used to find the critical path.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: