4. A company that operates 10 hours a day manufactures two products on three sequential processes. TIle
Question:
4. A company that operates 10 hours a day manufactures two products on three sequential processes. TIle following table summarizes the data of the problem:
Minutes per unit Product 1
2 Process 1 10 5
Process 2 6
20 Process 3 8
10 Unit profit
$2
$3 Determine the optimal mix of the two products.