*5. In the project of Example 6.5-2 (Figure 6.42), assume that the durations of activities B and...
Question:
*5. In the project of Example 6.5-2 (Figure 6.42), assume that the durations of activities B and F are changed from 6 and 11 days to 20 and 25 days, respectively.
(a) Determine the critical path.