*6. Figure 5.6 gives a schematic layout of a machine shop with its existing work centers designated...
Question:
*6. Figure 5.6 gives a schematic layout of a machine shop with its existing work centers designated by squares 1,2,3, and 4. Four new work centers, I, II, III, and IV, are to be added to the shop at the locations designated by circles
a, b,
c, and
d. The objective is to assign the new centers to the proposed locations to minimize the total materials handling traffic between the existing centers and the proposed ones. Table 5.43 summarizes the frequency of trips between the new centers and the old ones. Materials handling equipment travels along the rectangular aisles intersecting at the locations of the centers.
For example, the one-way travel distance (in meters) between center 1 and location b is 30 + 20 "" 50 m.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: