7 For Example 6 of Chapter 8, let A number of days duration of A is

Question:

7 For Example 6 of Chapter 8, let A  number of days duration of A is reduced, B  number of days duration of B is reduced, and so on. Suppose that the cost of crashing each activity is as follows:

A, 5A2; B, 20B2; C, 2C2; D, 20D2; E, 10E2; F, 15F2 and that each activity may be “crashed” to a duration of 0 days, if desired. Formulate an NLP that will minimize the cost of finishing the project in 25 days or less.