Four jobs must be processed on a single machine. The time required to process each job and

Question:

Four jobs must be processed on a single machine. The time required to process each job and the date the job is due are shown in Table 63. The delay of a job is the number of days after the due date that a job is completed (if a job is completed on time or early, the job’s delay is zero). In what order should the jobs be processed to minimize the total delay of the four jobs?