The table that follows shows the activities required to construct a new computer laboratory, along with their
Question:
The table that follows shows the activities required to construct a new computer laboratory, along with their estimated durations (in weeks)
and predecessor activities.
Activity Time Predecessors Order furniture (OF) 1 None Order computers (OC) 1 None Order software (OS) 1 OC Furniture delivery (FD) 6 OF, P Computer delivery (CD) 3 OC, AF Software delivery (SD) 2 OS Assemble furniture (AF) 1 FD Install computers (IC) 1 CD Install software (IS) 1 IC, SD Wire room (W) 2 None Paint room (P) 1 W Perform
(a) through
(e) of Exercise 9-26, assuming that the lab must be completed in 17 weeks.