Part X requires machining on a milling machine (operations A and B are required). Find the number

Question:

Part X requires machining on a milling machine (operations A and B are required).

Find the number of machines required to produce 3000 parts per week. Assume the company will be operating five days per week, 18 hours per day. The following information is known:

image text in transcribed

Note: The milling machine requires tool changes and preventive maintenance after every lot of 500 parts. These changes require 30 minutes.