Suppose that in Problem 2.20, each process was able to reduce its scrap estimate by 5%. What
Question:
Suppose that in Problem 2.20, each process was able to reduce its scrap estimate by 5%. What would the percent change in the requirement for each input be? What significance can this have on the process designer’s decision making process? (Hint: There are two ways of looking at this problem, either from the estimation perspective or from the continuous improvement perspective.)