In the crashing model in Example 15.3, we assumed that the cost per day crashed is constant.

Question:

In the crashing model in Example 15.3, we assumed that the cost per day crashed is constant. This is often unrealistic. For example, it might cost $300 to decrease the duration of an activity from 10 days to 9 days, but it might cost $450 to reduce it from 9 days to 8 days. One possible way to model this is to assume that the crashing cost, c(d), for reducing the duration by d days is a quadratic: c

(d)  cd2 for some constant c 

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Practical Management Science

ISBN: 9781111531317

4th Edition

Authors: Wayne L. Winston, S. Christian Albright

Question Posted: