Cohen Industrial Products uses 2,100 switch assemblies per month and then reorders another 2,100. The relevant carrying
Question:
Cohen Industrial Products uses 2,100 switch assemblies per month and then reorders another 2,100. The relevant carrying cost per switch assembly is $20 every year, and the fixed order cost is $300. The plant operates 250 days in a year and maintains a safety stock of 2 days’ worth of switch assemblies since the lead time to receive orders is 3 days. Calculate the economic order quantity (EOQ) and the reorder point.