A company is aware that the mean cost of repairs on production machines is at least $625

Question:

A company is aware that the mean cost of repairs on production machines is at least $625 a week. After a program to train employees on using the machines more effectively, the next 25 weeks are sampled and a mean of $600 and a standard deviation of $34.37 is obtained. Test if the training program worked at a significance level of 0.01, if the costs follow a normal distribution.