14. Sample observations of an industrial job were obtained over a 40-hour week. During the week, the
Question:
14. Sample observations of an industrial job were obtained over a 40-hour week. During the week, the worker produced a total of 280 assemblies and was rated at 135% performance. Further, the sample showed that the worker was not working 20% of time. The allowances for this type of work total 10%.
(a) Determine the normal time for task.
(b) Determine standard time.