Consider the following flow shop scheduling problem: Processing Time Job Machine 1 Machine 2 Machine 3 1
Question:
Consider the following flow shop scheduling problem:
Processing Time Job Machine 1 Machine 2 Machine 3 1 4 5 11 2 12 2 6 3 8 10 14 4 11 11 3 Check whether Johnson's rule can be applied. If not, solve the problem using Palmer's heuristic.