Consider the following problem of project scheduling. Obtain a schedule which will minimize the peak manpower requirement
Question:
Consider the following problem of project scheduling. Obtain a schedule which will minimize the peak manpower requirement and also smooth out period to period variation of manpower requirement.
Activity Duration
(Weeks)
Manpower Requirement 1-2 4 9 1-3 8 5 2-3 10 7 2-4 6 6 3-4 9 8 3-5 5 12 4-5 7 7.