Consider the manufacture of a toy. The master production schedule to manufacture the toy is given in

Question:

Consider the manufacture of a toy. The master production schedule to manufacture the toy is given in the following table.

Master Production Schedule Week 1 2 3 4 5 6 7 8 Demand 200 — 100 175 300 200 — 250 The bill of materials structure is given in the following figure.image text in transcribed

The details of Bill of Materials along with economic order quantity and stock on hand for the final product and subassemblies are shown in the following table.
Details of Bill of Materials Part Required Order Quantity No. of Units Lead Time (Week)
Stock on Hand A 350 1 2 200 B 450 1 1 400 C 400 1 1 375 D 375 1 1 250 E 400 1 2 425 Complete the material requirements plan for the main product A as well as for the subassemblies B, C, D and E.AppendixLO1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: