Question: After a change request is submitted, all of the following steps occur prior to being reviewed by the change control board except for which one?
After a change request is submitted, all of the following steps occur prior to being reviewed by the change control board except for which one?
A. The change request is recorded in the change log.
B. Analysis of the impacts of the change is performed.
C. Specific elements of the project, such as additional equipment needs, resource hours, quality impacts, and more, are analyzed.
D. Update the appropriate project management planning document to reflect the change.