Question: Your Scrum team's velocity rate is 24 story points per iteration. There are 165 total story points. Which of the following statements are true regarding
Your Scrum team's velocity rate is 24 story points per iteration.
There are 165 total story points. Which of the following statements are true regarding this question? (Choose two.)
A. Velocity is used to estimate the capacity of the Scrum team.
B. This information can be tracked on a burndown chart.
C. The project needs 7 iterations to complete all of the work of the project.
D. A Kanban board can display this information.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock