1. Given the SCFA standard and the estimated SCFA for the footings, what is the estimated labor...
Question:
1. Given the SCFA standard and the estimated SCFA for the footings, what is the estimated labor hours to install the footings?
Bill Asher, the estimator for Melbourne Construction Company, is currently estimating the days required to install the wall footings in the foundation of a hotel building. As is common for many of the activities in construction projects, he will develop the estimate using labor productivity standards.
Architectural drawings for the hotel indicate that the square foot contact area (SFCA) for the formwork footings is 13,340 sq. ft. (1,239 m2). Installation of footings is considered “standard,” so Bill refers to a manual of labor hour standards to estimate the total labor hours required for the task. The manual indicates that for the footings specified for the hotel, the standard is 0.066 labor hours per SFCA.
Step by Step Answer:
Project Management For Engineering Business And Technology
ISBN: 9780367277345,9781000092561
6th Edition
Authors: John M. Nicholas , Herman Steyn